Project Overview:

To improve grid reliability for local residents during peak summer demand, Kent Power installed a 2 MW portable battery system at the Substation. The project supports system resiliency and provides additional capacity during high-temperature periods that place stress on the electrical network.

Project Outcomes:

  • Installed 2 MW Battery Energy Storage System (BESS) to stabilize demand during peak load.
  • Constructed 58-P1 and 3-024A21 reinforced concrete foundations for equipment support.
  • Set one Class 4 distribution pole with integrated control cabinets.
  • Installed 8 ground rod locations for system grounding and fault protection.
  • Routed and connected all 2” conduits linking battery containers for full electrical continuity.
  • Completed installation safely and efficiently to support utility readiness for summer peak demand.